Engineer delay & winter work
Miss Nov 15 drawings, lose the pour window and foundation acceptance.
Lock commitment by Oct 28. Reserve crews.
Require a cold weather protection plan.
Miss Nov 15 drawings, lose the pour window and foundation acceptance.
Lock commitment by Oct 28. Reserve crews.
Require a cold weather protection plan.
PO unsent. Supplier silent 8 days. Eight week lead time.
Issue PO Oct 26. Verify release Oct 28.
Pull alternate quotes this week.
Six weeks transit. Jan 14 target. Jan 21 delivery limit.
Appoint forwarder now. Reserve sailing by Nov 6.
Price alternate port & expedited trucking.
Needs: Manufacturer loads, survey, soil info.
Needs: Complete engineering inputs, anchor details.
Needs: Local requirements, stamped drawings.
Needs: Drawings, permits, excavation, rebar inspection.
Needs: Strength results, anchor survey, inspection records.
Needs: Approved quote, payment terms. Supplier silent 8 days.
Needs: Oct 28 release. Eight weeks lead time after release.
Needs: Approved dimensions, electrical specs.
Needs: Cargo dimensions, importer, route.
Needs: Inspection, packing, confirmed booking.
Needs: Dec 3 departure, six weeks transit, customs.
Needs: Delivered inventory, packing lists.
Needs: Accepted foundations, utilities, access, permits.
Needs: Jan 29 readiness release.